Timeline 2005 - 2007
2005
- 04.02.2005
Tender landscape architecture competition two parks at the Friedrichswerder more (in German)
- 01.03.2005
Start of demolition apartment building at Luisenstraße (Luisenblock-West)
- 07.03.2005
Start of construction 1st construction section of the streets in the Townhouse-Quarter (Jägerstraße, Kleine Jägerstraße, Caroline-von-Humboldt-Weg, Alte Leipziger Straße) more (in German)
- 06.04.2005
Start rebuilding Unter den Linden between Humboldt-University and Hinter dem Gießhaus including Neue Wache and Kronprinzenallee
- 10.04.2005
Opening relocated Behrenstraße (at the American Embassy)
- 14.04.2005
Completion clearance of the Hafenplatz at the Haus der Kulturen der Welt
- 27.04.2005
Traffic opening Gertrud-Kolmar-Straße/Cora-Berliner-Straße
- 02.05.2005
Opening Margarete-Steffin-Straße
- 04.05.2005
Completion and handover 1st construction section of the streets in the Townhouse-Quarter (Jägerstraße, Kleine Jägerstraße, Caroline-von-Humboldt-Weg, Alte Leipziger Straße) more (in German)
- 09.05.2005
Traffic opening Hugo-Preuß-Brücke
- 09.05.2005
Traffic opening Rahel-Hirsch-Straße
- 10.05.2005
Inauguration of the "Monument for murdered Jews of Europe" more (in German)
- 19.05.2005
Start new building Adele-Schreiber-Krieger-Straße (lane and pavement) 2nd construction section from supply-tunnel to Luisenstraße
- 01.06.2005
Start of construction Kapelleuferpromenade
- 01.06.2005
Completion bluff Schiffbauerdamm up to Kronprinzenbrücke
- 02.06.2005
Finish expression of interest procedure regarding Pavillon am Reichstag more (in German)
- 16.06.2005
Establishment local plan I-215 Embassies Unter den Linden
- 27.06.2005
Establishment local plan I-216 Postblock
- 29.06.2005
Laying of the foundation stone for "Berlin Townhouses" more (in German)
- 30.06.2005
Traffic opening of the Gustav-Heinemann-Brücke
- 14.07.2005
Jury-conference realisation competition ULAP-terrain, 1st Prize: Rehwaldt - landscape architects more (in German)
- 20.07.2005
Start of construction Spreeuferpromenade
- 11.08.2005
Start of construction Zietenplatz/Mohrenstraße
- 12.08.2005
Traffic opening Jerusalemer Straße
- 25.08.2005
Landscape architecture competition two parks at the Friedrichswerder - Jury conference/Award 1st Prize: Büro Kiefer, Berlin more (in German)
- 05.09.2005
Traffic opening Unterbaumstraße
- 23.09.2005
Completion Spreeplatz at the Marie-Elisabeth-Lüders-Haus
- 10.10.2005
Start of construction Markgrafenstraße (Leipziger Straße to Mohrenstraße)
- 21.11.2005
Traffic opening Hannah-Arendt-Straße
- 30.11.2005
Completion demolition apartment block at the Luisenstraße
- 16.12.2005
130th and last coordination-consultancy regarding: Pariser Platz, Innerer Spreebogen and Lehrter Bahnhof (urban infrastructure)
- 19.12.2005
Opening Friedrich-List-Ufer
- 21.12.2005
Opening Platz des 18. März/Ebertstraße South
Seitenanfang
2006
- 07.01.2006
Start new building Voßstraße (1st construction section)
- 16.01.2006
Start of construction Washingtonplatz/Europaplatz (1st section of extension)
- 16.02.2006
Establishment local plan I-202 a Ministergärten
- 17.02.2006
Start of construction Bus-reversing-loop Hauptbahnhof
- 02.03. - 28.07.2006
Execution noise protection measures at the Hannah-Arendt-Straße
- 27.03.2006
Start of construction Pavillon am Reichstag
- 28.04.2006
Establishment local plan I-207 Ministry of Foreign Affairs
- 05.05.2006
100th Consultancy workgroup frame coordination Lehrter Bahnhof
- 11.05.2006
Completion Kapelleuferpromenade and Spreeuferpromenade more (in German)
- 24.05.2006
Traffic opening Unter den Linden between Humboldt-University and Hinter dem Gießhaus
- 24.05.2006
Opening Washingtonplatz/Europaplatz (1st extension section) and bus-reversing-loop Hauptbahnhof (1st section of construction)
- 09.06.2006
Opening Pavillon am Reichstag
- 09.06.2006
Traffic opening Voßstraße (1st construction section)
- 16.06.2006
Establishment local plan II-200 d Platz der Republik/Reichstag
- 22.06.2006
Establishment local plan II-201 b Zellengefängnis
- 26.06.2006
Establishment local plan I-214 Federal Ministry for Labour and Social Matters
- 26.06.2006
Start of construction Alexanderufer
- 03.07.2006
Establishment local plan I-208 Friedrichswerder North
- 12.07.2006
Completion Markgrafenstraße
- 19.07.2006
Completion landscaping Bettina-von-Arnim-Ufer and staircase Hafenplatz
- 21.08.2006
Start of construction Emma-Herwegh-Straße
- 25.08.2006
Traffic opening Unter den Linden Kronprinzenallee
- 25.09.2006
Start design schoolyard 10th primary school at the Brandenburger Tor
- 01.10.2006
Start of construction Extension of the Federal Ministry for Nutrition, Agriculture and Consumer Protection more (in German)
- 09.10.2006
Start new building of the Federal Ministry for Family, Seniors, Women and Youth
- 14.11.2006
1st Consultancy of the workgroup overall project coordination Breite Straße including coordination of urban infrastructure
- 20.12.2006
Opening Emma-Herwegh-Straße
Seitenanfang
2007
- 15.03.2007
Start competition redesign Neustädtischer Kirchplatz more (in German)
- 26.03.2007
Start restoration Schinkelplatz in line with historic preservation practices
- 16.04.2007
Start 2nd construction section of the Townhouse-Quarter-Streets (Jägerstraße, Kleine Jägerstraße, Caroline-von-Humboldt-Weg, Alte Leipziger Straße) and start renovation and new building Niederwallstraße more (in German)
- 16.04.2007
Start landscaping Friedrichswerder West (two parks at the Friedrichswerder) more (in German)
- 02.05.2007
Start of 2nd section of construction Clara-Jaschke-Straße, Katherina-Paukes-Straße, Bela-Benz-Straße, Agnes-Zahn-Harnack-Straße, Ilse-Scheffer-Straße, Ella-Trebbe-Straße (at the Hauptbahnhof)
- 03.05.2007
Completion design schoolyard 10th primary school at the Brandenburger Tor
- 07.05.2007
Start of construction S-Bahn parallel (Section Alexanderufer - Unterbaumstraße - still under construction)
- 14.05.2007
Start of road works Friedrichsgracht
- 06.06.2007
Traffic opening Zietenplatz/Mohrenstraße
|