Timeline 1998 - 1999


1998

  • 29.01.1998
    Traffic opening Reinhardtstraße from Kronprinzenbrücke to DB-Brücke and the connection Unterbaumstraße
  • 05.03.1998
    Establishment-Resolution local plan I-212 Federal Ministry of Justice
  • 06.03.1998
    Opening of the Brandenburger Tor for a period of eight months
  • 10.03.1998
    Completion and structure-acceptance Hausvogteiplatz 12
  • 27.03.1998
    Topping-out ceremony Pariser Platz 3, DZ-Bank
  • 07.04.1998
    Laying of the foundation stone extention Ministry of Foreign Affairs
  • 24.04.1998
    Start new building Mauerstraße from Bethlehemkirchplatz up to Leipziger Straße
  • 28.04.1998
    Laying of the foundation stone house building Moabiter Werder
  • 12.05.1998
    Laying of the foundation stone Marie-Elisabeth-Lüders-Haus (Luisenblock)
  • 14./15.05.1998
    Jury Provincial Representative Brandenburg / Mecklenburg-Vorpommern, 1st Prize: Gerkan, Marg and Partner
  • 18.05. -16.06.1998
    Early civic participation local plan I-212 Federal Ministry of Justice
  • 15.06.1998
    Start new building Paul-Löbe-Allee at the German Bundestag
  • 22.06.1998
    Start new building Alice-Behrendt-Straße
  • 22.06.1998
    Start new building Ingeborg-Drewitz-Allee up to Joachim-Karnatz-Allee
  • 25.06.1998
    Resolution of the Berlin House of Representatives regarding the establishment of the local plan I-210 Reinhardtstraße
  • 29.06.1998
    Resolution of the Berlin House of Representatives regarding the establishment of the local plan I-202 b Ministergärten
  • 29.06.1998
    Ground breaking ceremony British Embassy, Wilhelmstraße
  • 29.06.1998
    Start new building Scheidemannstraße
  • 30.06.1998
    Traffic opening Unter den Linden from Pariser Platz to Glinkastraße first section central promenade
  • 01.07.1998
    Topping-out ceremony Federal Ministry of Justice
  • 10.07.1998
    Laying of the foundation stone French Embassy, Pariser Platz
  • 21.07.1998
    Start new building Ebertstraße (Reichstag environment)
  • 03.08.1998
    Start new building Luisenstraße from Marschallbrücke to S-Bahn viaduct
  • 18.08.1998
    Start of work Spreekanaluferweg (Staatsratsgarten/Friedrichsgracht)
  • 01.09.1998
    Topping-out ceremony Deutscher Industrie- und Handelskammertag
  • 14.09.1998
    Start new building Ebertstraße North from Dorotheenstraße to Platz des 18. März
  • 17.09.1998
    Topping-out ceremony house building Moabiter Werder
  • 21.09.1998
    Start new building Reichstagsufer West, first section of construction from Wilhelmstraße to Bunsenstraße
  • 22.09.1998
    Start new building Wilhelmstraße North from Marschallbrücke to Unter den Linden
  • 12.10. - 06.11.1998
    Early civic participation local plan I-213 Press and Information Office more (in German)
  • 13.10.1998
    Start new building Otto-von-Bismarck-Allee
  • 14.10.1998
    Start new building first section of construction Konrad-Adenauer-Straße between Kronprinzenbrücke and Otto-von-Bismarck-Allee
  • 14.10.1998
    Start restoration planning Mohrenkolonnaden
  • 31.10.1998
    Completion culture-debris removal (second section)
  • 06.11.1998
    Topping-out ceremony extension Ministry of Foreign Affairs
  • 23.11.1998
    Inauguration official building of the Office of the Federal President by reason of the start of the operational functions
  • 02.12.1998
    Traffic opening Mauerstraße from Bethlehemkirchplatz to Leipziger Straße
  • 08.12.1998
    Establishment-Resolution local plan I-216 Postblock
  • 11.12.1998
    Resolution of the Berlin House of Representatives regarding the local plan I-206 ARD-Capital Studio

Seitenanfang


1999

  • 07.01.1999
    Establishment-Resolution local plan I-215 Embassies Unter den Linden
  • 26.01.1999
    Laying of the foundation stone Bundespressekonferenz
  • 28.01.1999
    Topping-out ceremony day-care center of the German Bundestag
  • 04.02.1999
    Laying of the foundation stone Office- and Business-House Pariser Platz 4a (ABG)
  • 15.02.1999
    Topping-out ceremony Provincial Representatives of the Free State of Saxony
  • 05.03.1999
    Establishment-Resolution local plan I-214 Federal Ministry for Labor and Social Affairs
  • 26.03.1999
    Laying of the foundation stone Provincial Representatives of Rhineland-Palatinate
  • 27.03.1999
    Tunnelling under the River Spree (subterrestrial site development North of the German Bundestag)
  • 01.04.1999
    Establishment-Resolution local plan I-218 Breite Straße
  • 12.04.1999
    Opening traffic areas around the Reichstag by SenBauWohnV
  • 12.04.1999
    Traffic opening Ebertstraße (Reichstag environment)
  • 14.04.1999
    Inauguration of the Reichstag (20 - 25 April 1999: Reichstag Open Day, 22 May 1999: Public festivity in front of the Reichstag)
  • 17.05. - 11.06.1999
    Early civic participation local plan I-215 Embassies Unter den Linden
  • 18.05.1999
    Start new building Reinhardtstraße from Kronprinzenbrücke to S-Bahn-Subway Connection Kapelleufer, Schiffbauerdamm and S-Bahn-parallel
  • 21.05.1999
    Topping-out ceremony British Embassy, Wilhelmstraße
  • 01.06.1999
    Start new building Unterwasserstraße from Werderstraße to Oberwasserstraße
  • 01.06.1999
    Start new building Oberwasserstraße including Kleine Kurstraße from Unterwasserstraße to southern Kurstraße
  • 16.06.1999
    Laying of the foundation stone Provincial Representatives Saarland
  • 18.06.1999
    Inauguration Provincial Representatives Free State of Thuringia
  • 25.06.1999
    Topping-out ceremony Bundesrat (Federal Assembly)
  • 30.06.1999
    Laying of the foundation stone Provincial Representatives Schleswig-Holstein and Lower Saxony
  • 01.07.1999
    Start rebuilding Leipziger Straße from intersection Mauerstraße to Preußisches Herrenhaus (Federal Assembly)
  • 02.07.1999
    Topping-out ceremony Federal Ministry for Labour and Social Affairs
  • 02.07.1999
    The Combined Commission of Federation/Berlin, Topics: among other things, beginning of work in the federal capital, the Schloßplatz project, and the Bauakademie
  • 12.07.1999
    Start of construction "Rasenschloss" on the palace area
  • 12.07.1999
    Traffic opening Luisenstraße from Marschallbrücke to S-Bahn-viaduct
  • 14.07.1999
    Start of the reconstruction of the Mohrenkolonnaden in line with generally accepted conservation practice
  • 21.07.1999
    Hand-over of keys of the day-care center of the German Bundestag
  • 23.07.1999
    Start new building Werderstraße (Werderscher Markt) from Schleusenbrücke to Kurstraße
  • 26.07.1999
    Traffic opening lane Unterwasserstraße from Werderstraße to Oberwasserstraße
  • 01.08.1999
    Start construction of safety-devices at the Reichstag (immersible bollards)
  • 02.08.1999
    Traffic opening lane Oberwasserstraße including Kleine Kurstraße from Unterwasserstraße to southern Kurstraße
  • 02.08.1999
    Start new building Schiffbauerdamm
  • 02.08.1999
    Start new building first construction section Margarethe-Steffin-Straße from Reinhardtstraße to Luisenstraße
  • 02.08.1999
    Start new building Adele-Krieger-Schreiber-Straße (Nordallee), first construction section from the River Spree to the supply tunnel at the Marie-Elisabeth-Lüders-Haus more (in German)
  • 07.08.1999
    Start new building Heinrich-von-Gagern-Straße
  • 07.08.1999
    Start new building Floraallee (Izak-Rabin-Straße)
  • 01.09.1999
    Laying of the foundation stone for the establishment of the "Musterecke" Bauakademie
  • 02.09.1999
    Traffic opening Alice-Behrendt-Straße
  • 02.09.1999
    Traffic opening Ingeborg-Drewitz-Allee - Joachim-Karnatz-Allee
  • 03.09.1999
    Topping-out ceremony Provincial Representatives Rhineland-Palatinate
  • 06.09.1999
    Start new building Paul-Löbe-Allee at the Federal Chancellery - Southern Lane
  • 06.09.1999
    Start new building Große Querallee
  • 10.09.1999
    Completion "Rasenschloss" on the palace area
  • 17.09.1999
    Topping-out ceremony Pariser Platz 4a (ABG)
  • 17.09.1999
    Topping-out ceremony Provincial Representatives Hesse
  • 21.09.1999
    Start new building northern Kurstraße - 5th construction section Werderstraße to northern edge Reichsbank building
  • 21.09.1999
    Start new building southern Kurstraße from northern edge Reichsbank building to Gertraudenstraße
  • 23.09.1999
    Lehrter Bahnhof
  • 24.09.1999
    Traffic opening 1st construction section Konrad-Adenauer-Straße between Kronprinzenbrücke and Otto-von-Bismarck-Allee
  • 27.09.1999
    Start new building bus parking sites
  • 27.09. - 27.10.1999
    Early civic participation local plan I-214 Federal Ministry for Labour and Social Affairs and local plan I-216 Postblock
  • 30.09.1999
    Ground breaking ceremony Platz der Republik mehr
  • 04.10.1999
    Start new building Reichstagsufer East from Ebertplatz to Wilhelmstraße
  • 22.10.1999
    Topping-out ceremony Federal Chancellery
  • 26.10.1999
    Topping-out ceremony Provincial Representatives Free State of Thuringia
  • 02.11.1999
    Traffic opening lane Unterwasserstraße from Werderstraße to Oberwasserstraße
  • 02.11.1999
    Traffic opening pavement Oberwasserstraße including Kleine Kurstraße from Unterwasserstraße to southern Kurstraße
  • 03.11.1999
    Topping-out ceremony Paul-Löbe-Haus
  • 08.11.1999
    Start new building Eastern by-pass Swiss Embassy
  • 10.11.1999
    Laying of foundation stone Hungarian Embassy, Unter den Linden
  • 12.11.1999
    Inauguration of the buildings Deutscher Industrie- und Handelskammertag
  • 15.11.1999
    Start new building Reichstagsufer West - 2nd construction section Bunsenstraße up to Neustädtische Kirchstraße
  • 16.11.1999
    Traffic opening lane northern Kurstraße - 5th construction section from Werderstraße to northern Edge Reichsbank building
  • 16.11.1999
    Traffic opening lane Werderstraße from Schleusenbrücke to Kurstraße/Unterwaserstraße
  • 17.11.1999
    Building license sports field and multi-purpose-building In den Ministergärten
  • 30.11.1999
    Traffic opening bus parking sites
  • 17.12.1999
    Opening Spreekanaluferweg (Staatsratsgarten/Friedrichsgracht